US Made Supply

✓ Verified

"Product and application as des..."

✓ Verified

"very high quality. easy to app..."

✓ Verified

"So far - love the product and ..."

Roofing & Roofs
Flat or Low Slope

SB 721 Balcony Repair Contractor Bid Guide

How to scope, price, and submit a defensible bid for SB 721 and SB 326 balcony repair work in California

Last updated: April 22, 2026


Overview

This guide is for contractors preparing a bid on SB 721 or SB 326 balcony repair work, and for owners and HOA boards evaluating bids that come back. It covers how to scope the repair, which CSLB license classifications actually cover the work, how to structure a bid that survives hidden substrate damage, what submittals belong with the proposal, how warranty stacks, and what inspector coordination the general contractor is responsible for.

It does not cover the inspection itself. The inspection is a separate scope, performed by a qualified professional under different statutory requirements. For background on the inspection side and what triggers a repair, see the California Balcony Law hub. To interpret an inspection report before scoping a bid, see Understanding Your SB 721 Inspection Report.

Statutes covered: SB 721 is codified at Health & Safety Code § 17973. SB 326 is codified at Civil Code § 5551. AB 2579 (2024) extended the SB 721 initial deadline to January 1, 2026. AB 2114 (2024) added civil engineers to the SB 326 inspector list. Repair scope and bid mechanics are largely the same across the two statutes; the procedural differences are noted where they matter.

License Classifications for SB 721 / SB 326 Repair Work

Under Business & Professions Code § 7028, performing contracting work outside of the classifications a license authorizes is a misdemeanor and voids mechanics lien rights. SB 721 repair work typically spans framing, waterproofing, flashing, guardrails, and finishes. Almost always more than one trade. The prime contractor must either hold a classification that covers the full scope or sub-contract the parts it does not cover to appropriately licensed specialty contractors.

ClassScope (summarized)Covers in SB 721 repairDoes not cover
B. General BuildingStructures requiring two or more unrelated trades. Per B&P Code § 7057; 16 CCR § 832.02.Full-scope prime contractor on a multi-trade SB 721 repair (framing + waterproofing + flashing + guardrails).Single-trade work unless framing/carpentry is part of the scope (and framing alone does not satisfy the two-trades test).
C-5. Framing / Rough CarpentryWood framing, ledgers, joists, posts, beams, structural sheathing. 16 CCR § 832.05.Structural-only repairs where the waterproofing is handled by a separately licensed specialty contractor.Waterproofing, membrane coating, sheet-metal flashing.
C-33. Painting & DecoratingPaints, textures, fabrics, and "any other vehicles, mediums and materials which adhere by evaporation." 16 CCR § 832.33.Evaporative-cure elastomeric topcoats on an existing waterproofed deck; decorative finish work.Reactive two-component traffic coatings (urethanes, PMMAs) are a poor fit for the "adhere by evaporation" scope language.
C-39. RoofingProducts that "seal, waterproof and weatherproof structures," explicitly including urethane foam and membrane materials. 16 CCR § 832.39.Walking-deck waterproofing membranes and coatings, deck-to-wall flashing integration with weather-resistive barrier.Structural framing or ledger replacement.
C-61 / D-12. Synthetic ProductsFiberglass, plastic, vinyl and epoxy products; resin and epoxy application; synthetic caulking and sealants. 16 CCR § 832.61 + classification deputy rulings.Epoxy / resin repair of specific substrate or patching scopes.Not a clean fit for walking-deck traffic coatings; D-12 does not name deck coating.
C-61 / D-64. Non-SpecializedResidual specialty classification for work that does not fit any other C-class. 16 CCR § 832.64.Only defensible when the scope does not fit C-33, C-39, or D-12.Any scope that another classification arguably covers.

Classification gray zone. CSLB has never issued a stand-alone "deck waterproofing" classification. For walking-deck membrane and coating work, C-39 is the most defensible fit because § 832.39 explicitly names waterproofing and membrane materials. C-33 is a fit only for evaporative-cure topcoats. D-12 covers epoxy/resin but does not cleanly cover traffic coatings. D-64 is a last-resort fallback. For edge cases, confirm directly with the CSLB Classifications Deputy (classifications@cslb.ca.gov). The position above is editorial guidance, not legal advice.

C-27 (Landscape) does not cover SB 721 repair. Per B&P Code § 7026.1 and 16 CCR § 832.27, the C-27 classification is limited to landscape architecture, planting, irrigation, lighting, and incidental hardscape. It does not authorize structural or waterproofing repair of exterior elevated elements. If a landscape-focused bidder proposes to do deck waterproofing on a C-27, treat it as a disqualifier.

Inspector-qualification classifications (A, B, or C-5 with 5+ years of multistory wood-frame experience) under § 17973(a) are a separate question from who can perform the repair. See the Inspector Coordination section for how the inspector and repair contractor roles interact.

Typical Scope-of-Work Components

A complete SB 721 or SB 326 repair bid usually covers each of the following. Omitting any of them is the fastest way to create a change-order cascade after demolition exposes the substrate.

Demolition and site protection

Controlled demolition of the walking surface, membrane, and any damaged framing identified in the inspection report. Tenant accommodations (temporary balcony access, noise windows), temporary guardrails per Cal/OSHA during open-deck work, dust and debris containment, and dumpster access all belong in the base bid. Not treated as a separate owner responsibility.

Structural repair

Replacement of damaged ledgers, joists, beams, posts, and connectors. Ledger reattachment per engineered detail when the original connection is unknown or deteriorated. Connectors are typically upgraded to stainless steel or hot-dip galvanized where corrosion was a factor in the original damage.

Waterproofing system

The primary waterproofing architecture is either non-floating or floating. Non-floating systems. Cementitious-acrylic multi-layer assemblies, liquid-applied elastomerics, polyurethane and PMMA traffic coatings. Are mechanically and chemically bonded to the substrate so the waterproofing layer is also the walking surface. Floating systems. Sheet membranes (SBS/APP modified bitumen, PMMA sheets, PVC, TPO). Are loose-laid or edge-attached under a separate walking surface like pavers or raised decking. ICC-ES AC39 evaluates walking-deck waterproofing systems; specifying "per ICC-ES ESR-XXXX" binds the applicator to the specific evaluated assembly. See the deck waterproofing guide for system architectures and deck coating options for coating-type comparisons.

Flashing

Deck-to-wall flashing, deck-edge flashing, penetrations, and door thresholds. Galvanized sheet metal of 26 gauge minimum is an industry baseline for bonded walking-deck systems (Deck Flex W.M. and W.F. architectural details under ESR-3672 specify 26 ga. as the minimum). Drip-edge flashing is typically specified as 1/16" to 1/8" rise on bonderized sheet metal. Flashing must be integrated with the wall weather-resistive barrier in the correct overlap sequence; a mid-wall flashing installed over the WRB, for example, is a warranty disqualifier on most systems.

Slope and drainage

The repaired deck must drain. 1/4" per foot minimum positive slope to drains or edge is the baseline for bonded walking-deck systems. If the existing structure does not drain. Or drains toward the building. The repair scope must re-slope the plywood substrate, typically with tapered shims or a cementitious leveling layer, before the waterproofing goes on. Call this out in the bid; re-slope work is easy to miss at walkthrough and expensive to add mid-project.

Guardrail and handrail

Post replacement, anchor reset, and code-compliant height and infill per CRC R312 / CBC § 1015. Where anchors penetrate the new waterproofing, base-plate flashing and sealant detailing is part of this scope, not the waterproofer's. Guardrail scope is a common omission in lump-sum bids . Bidders assume the owner handles it, owners assume it's in the base bid.

Electrical reinstatement

GFCI outlets, exterior lighting, and low-voltage runs that were disconnected during demolition. Typically subbed to a licensed electrical contractor (C-10); call out the sub arrangement in the bid.

Painting and finish

Repainting soffits, fascia, and adjacent wall surfaces disturbed by the repair. Color-matching on existing buildings is rarely a perfect match; include allowance language or a tolerance statement.

Testing and punch

Flood test or spray test of completed waterproofing (48-hour retention is typical). Slope check. Adhesion test (ASTM D4541 pull-off) where the specification calls for it. Final punch walk with the owner, the inspector (for re-inspection sign-off), and the manufacturer field rep if a joint warranty is being issued.

Bid Format: Lump-Sum + Unit-Price + Allowance Hybrid

A pure lump-sum bid on SB 721 repair work rarely works. The contractor cannot see what's under the membrane until demolition starts, and the inspection report. While useful. Is a visual observation of the exposed condition, not an exhaustive destructive survey. The bid format that holds up is a three-part hybrid: lump-sum for the knowable scope, unit-price for the quantity-variable items, and allowance for the genuinely unknowable.

Bid structureApplies toWhy this structure
Lump-sum baseWaterproofing system (primer, base, fabric, topcoat), flashing installation, guardrail reset, painting, permits, supervisionQuantity is fixed once the repair area is defined. Absorb the risk at a known cost.
Unit-price per LF joistJoist replacement beyond the inspection-report quantityDemolition routinely exposes additional rot. Unit-price converts that into predictable reconciled cost instead of a change-order fight.
Unit-price per SF membraneAdditional deck area discovered to need re-membrane after walkthroughAdjacent decks often share a failure mode. Unit-price makes expanding scope clean.
Unit-price per guardrail postPost replacement and anchor resetCorrosion count is rarely visible pre-demo.
Allowance lineHidden substrate repair (sheathing replacement, ledger blocking, re-sloping)Genuinely unknowable at bid time. Owner funds the allowance, contractor reconciles to actuals at closeout. Any un-spent allowance returns to owner.

Change-order triggers. Spell out in the bid exactly what converts base-bid work into unit-price or allowance work. Common triggers: rot extending more than 6" beyond an area called out in the inspection report; dry rot or fungal damage in adjacent joists discovered during demolition; substrate that cannot hold fasteners per the membrane-system specification; re-sloping required to meet the 1/4" per foot minimum. Triggers that are not pre-defined become disputes.

Pricing ranges commonly cited in industry sources (illustrative, not CSLB data): waterproofing and resurfacing per balcony ~$1,500–$5,000; structural framing repair per balcony ~$3,000–$15,000+; railing replacement per unit ~$1,000–$4,000; full rebuild per unit ~$10,000–$30,000+. These are broad ranges. Regional labor rates, system specification, and site access all move the number significantly.

Submittals Required with the Bid

Submittal quality is a bid-evaluation signal. A bidder who submits the following with the proposal is demonstrating they have done the specification work; a bidder who says "we'll submit after award" is shifting that risk to the owner.

  • Product data sheets for the waterproofing system, flashing, sealants, and primary fasteners
  • ICC-ES Evaluation Report reference for the waterproofing system (for example, ESR-3672 for Deck Flex W.M. and W.F. under AC39). The ESR number binds the assembly that will be installed. See ICC-ES AC39 for what AC39 evaluates
  • Warranty registration forms for the manufacturer material warranty and, where applicable, the joint system warranty
  • Approved-applicator certification from the waterproofing manufacturer, with effective date and expiration
  • Shop drawings for structural repairs. Ledger connection detail, joist-hanger schedule, guardrail post anchorage
  • Material samples of the waterproofing topcoat color and texture
  • Proof of CSLB license, workers-comp coverage, and project-appropriate general liability limits
  • Bidder-named specialty sub-contractors with their CSLB license numbers verifiable at CSLB License Lookup

Permits and Engineered Drawings

CBC § 105.1 requires a permit for any repair, alteration, or replacement of a building or structure. Cosmetic work exempt under § 105.2 (painting, wallpaper, small sheds) does not apply here; any SB 721 or SB 326 repair that touches framing, ledger, guardrail anchorage, flashing, or membrane requires a permit from the local jurisdiction. HSC § 17973(g) reinforces this: "All necessary permits for repair or replacement shall be obtained from the local jurisdiction… and shall be subject to the California Building Standards Code."

The 120-day clock under § 17973(h)(2) is specifically 120 days to apply for the permit, not to complete the repair. Completion timing is set by the permit, the severity of the finding, and any inspector-directed emergency stabilization; do not bid the project on the assumption that all repairs must be finished within 120 days of the inspection report.

Stamped engineered drawings are required whenever a structural member is modified or replaced beyond a like-for-like in-kind replacement. Per CBC § 107.1 and § 1603, structural drawings for Group R occupancy repairs must be prepared by a California-licensed architect or civil or structural engineer. In practice, most jurisdictions require stamped plans the moment the repair deviates from in-kind replacement. For example, re-engineering a ledger connection because the original detail is unknown, upsizing joists, or adding a guardrail anchor that did not exist in the original construction. Confirm locally before pricing; some plan-check desks require stamps for all SB 721 repairs as a matter of policy.

The general contractor typically pulls the permit. When the owner pulls it under an owner-builder permit, the CSLB restriction under B&P Code § 7044 still applies. The owner cannot use an owner-builder permit to avoid hiring licensed contractors for the actual work.

Inspector Coordination

The inspection is not done when the report is delivered. The original inspector (or their firm) typically returns for pre-cover re-inspection of critical assembly points. Flashing integration, structural connectors, ledger reattachment. Before the waterproofing closes up the work. Build those re-inspection visits into the project schedule and the base bid. Leaving them as an owner-direct line item creates scheduling friction and invites a bidder to strip the cost out of their base to come in low.

Inspector-conflict rule under § 17973(g): "No recommended repair shall be performed by a licensed contractor serving as the inspector." A contractor who performed the SB 721 inspection cannot also bid or perform the repair on the same property. This is a strict statutory prohibition, not a conflict-of-interest preference. Bidders who did inspection work for the building must decline the repair RFP.

SB 326 has no analogous provision in Civil Code § 5551 because SB 326 inspectors are limited to architects and licensed engineers. Not contractors. So the conflict cannot arise the same way. Any firm that performed the SB 326 inspection still should not bid the repair; the professional-conflict norms for architects and engineers reach a similar result even without the statutory language.

Good inspector coordination on the general contractor side includes: at least 5 business days' notice before each re-inspection milestone; a hold-point schedule in the submittal package showing when the inspector is needed (substrate cleared, flashing installed, membrane applied, final); and a written completion letter from the manufacturer field rep that the inspector can attach to the final report.

Warranty Structure

A defensible SB 721 repair warranty is a three-layer stack. Each layer has a distinct obligor and a distinct scope. Collapsing them into a single "contractor guarantees the work for X years" statement almost always means the material side is unregistered. And therefore voided . From day one.

LayerObligorCoversTypical term
Manufacturer material warrantyCoating / membrane manufacturerDefects in the manufactured material. Conditional on approved applicator + registered project.5–10 years (Deck Flex W.F. = 5 years, W.M. = 10 years under ESR-3672 per published specification)
Applicator workmanship warrantyRepair contractor / specialty applicatorInstallation quality. Adhesion, coverage, detail execution.2–5 years
Combined system warrantyManufacturer + applicator, jointlyMaterial + workmanship, back-stopped by manufacturer field inspection during install.Negotiated per project; typically matches or extends the manufacturer material term.

Write each layer into the bid. Name the obligor, the term, the exclusions, and the registration requirement. Do not rely on "standard manufacturer warranty". "standard" is the registration-contingent one, and unregistered installs are the default failure mode. The bid should confirm registration will be filed within the manufacturer's window (typically 30 days of project completion) and that owner will receive a copy of the registration receipt.

Bidding SB 721 balcony repair? Need bid-ready materials pricing?

Non-floating ICC-ES AC39 systems + flashing + joist protection + fasteners priced for contractor bid. Drop-ship available. Typical turnaround: one business day.

or call 714-248-6555 · email partners@usmadesupply.com

Applicator Qualification

Most walking-deck ESRs condition manufacturer warranty. And in some cases the evaluation report itself. On installation by a manufacturer-trained, approved applicator. Verify the specific language on the ESR for the system being specified; it varies by report.

As a worked example, the Deck Flex W.M. (Class A) and W.F. (Class B) specification guides under ESR-3672 both require a two-part applicator test for bonded walking-deck installations:

  • Licensed contractor approved by the manufacturer (written certification on file, current)
  • Licensed specialty contractor in the business of applying elastomeric membrane roofing and waterproofing for a minimum of 5 years

This two-part test is representative of the approved-applicator standard for non-floating bonded systems. It is not a universal rule across all walking-deck ESRs, but it is a useful benchmark when evaluating a bidder: the 5-year elastomeric-membrane operating history is a gating criterion that separates specialty applicators from painting contractors who occasionally touch deck work.

Manufacturer quality-assurance procedures for approved-applicator projects typically include: written certification that the applicator is approved for this type and size of project; a pre-start site visit to inspect substrates (commonly with 5 days' notice); periodic review during waterproofing work with written exceptions; and a completion letter to the architect or owner indicating compliance. These QA steps are part of why the joint system warranty exists. The manufacturer has direct observation of the install.

Common Failure Modes in SB 721 Bids

The patterns below come up on almost every multi-balcony repair project. Each one is avoidable if the bid is structured deliberately.

Substrate damage underestimated

The inspection report is a visual observation of exposed conditions. Dry rot and galvanic corrosion routinely extend beyond the observed area. Lump-sum bids with no unit-price for joist replacement force contractors to either pad the base aggressively or fight over change orders after demolition.

Guardrail scope left ambiguous

Guardrail anchorage touches both structure and waterproofing. Each trade assumes the other has it. The result is either double-billed or zero-billed work, and code-height or infill violations get discovered at final inspection.

Weather-delay clauses are vague

Bonded waterproofing systems have temperature and humidity minimums at each coat. A rainy week can cost real schedule time. Define the no-fault weather-delay threshold explicitly (for example, "rain within 24 hours of planned application, ambient temp below system minimum, or substrate moisture above manufacturer spec") and how those days roll into the schedule.

Inspector re-inspection fees omitted

Re-inspection visits aren't free. If the bid doesn't carry them, the owner discovers the cost as a separate invoice from the inspector. Include them in the base with a named number of visits and a unit-price for additional visits beyond that.

Tenant notification and access

SB 721 buildings are occupied. The repair contractor does not have a private right of entry through the unit; access is the owner's responsibility, coordinated in advance. If the bid doesn't call out 72-hour notice requirements, quiet hours, or alternative-access provisions, expect schedule slippage.

Lump-sum on inherently variable work

Pricing joist replacement as lump-sum with a stated quantity, and then treating every additional joist as a change order, is the single most common source of SB 721 project disputes. Unit-price it up front.

Evaluating Bids: What Owners and HOAs Should Look For

This section is for the owner, property manager, or HOA board reviewing contractor bids. You do not need to evaluate framing calculations or coating chemistry. The questions below are surface-readable and catch most of the problems before they become construction-phase fights.

  • Verify the bidder's CSLB license status at CSLB License Lookup. Check for an active license, classifications that cover the full repair scope (or named sub-contractors who do), and no pending disciplinary actions.
  • Confirm the bid names a specific waterproofing system by ICC-ES ESR number, not just by product brand. "ESR-3672" is a verifiable reference; "Brand X deck coating" is not.
  • Confirm the bidder is listed on the manufacturer's approved-applicator roster with a current effective date, not just "we use that product."
  • Look for unit-price line items for joists (per LF), membrane (per SF), and guardrail posts. A pure lump-sum bid on SB 721 repair is a red flag.
  • Confirm warranty terms by layer. Material, workmanship, and (when applicable) joint system. With the manufacturer registration process written in.
  • Confirm that inspector re-inspection coordination is in the bidder's scope, with a named number of visits. Ask what happens if additional visits are needed.
  • Confirm none of the bidders performed the SB 721 inspection on your property. HSC § 17973(g) bars inspecting contractors from performing the repair.
  • Ask how the bidder handles weather delays, tenant access, and dust containment. The answers to these three questions tell you more about their operational maturity than the line-item total does.

Frequently Asked Questions

Can the contractor who performed the SB 721 inspection also bid the repair?

No. Health & Safety Code § 17973(g) states that "no recommended repair shall be performed by a licensed contractor serving as the inspector." A contractor who performed the inspection is barred from performing the repair on the same property. This is a statutory prohibition, not a conflict-of-interest preference. SB 326 has no analogous provision because SB 326 inspectors are restricted to architects and engineers, not contractors.

What CSLB license do I need to waterproof a balcony in California?

For walking-deck waterproofing, C-39 (Roofing) is the most defensible classification because 16 CCR § 832.39 explicitly names waterproofing and membrane materials. A B (General Building) license covers the full multi-trade repair as prime. C-33 covers evaporative-cure topcoats but is a poor fit for reactive two-component traffic coatings. D-12 (Synthetic Products) covers epoxy/resin work but does not cleanly cover traffic coatings. D-64 (Non-Specialized) is a last-resort fallback only when no other classification fits. For edge cases, confirm with the CSLB Classifications Deputy directly.

Do I need stamped engineered drawings for the repair?

Yes whenever a structural member is modified or replaced beyond in-kind replacement. Per CBC § 107.1 and § 1603, structural drawings for Group R occupancy must be prepared by a California-licensed architect or civil or structural engineer. Re-engineering a ledger connection, upsizing joists, or adding new guardrail anchors all typically require stamped plans. Many jurisdictions require stamps as policy on any SB 721 repair. Confirm locally before pricing.

What is the repair deadline after an SB 721 inspection?

Under HSC § 17973(h)(2), the owner has 120 days to apply for the repair permit. Not to complete the repair. The completion timeline is set by the permit, the severity of the finding, and any emergency stabilization directives from the inspector or local code enforcement. SB 721 civil penalties of $100 to $500 per day apply after a separate 180-day non-compliance window once repairs are required. Do not bid or plan the project on the assumption of a 120-day total turnaround.

Can I use a C-61/D-64 license for deck coating work?

Only when the scope does not fit any other specialty classification. D-64 is a residual Non-Specialized classification. If the work arguably fits C-33, C-39, or D-12, those are the correct classifications and D-64 is not defensible. CSLB takes the position that specialty classifications have priority over D-64.

What happens if manufacturer warranty registration is skipped?

The material warranty is voided from the start. Most walking-deck manufacturers condition their warranty on both approved-applicator install and registration of the specific project within a defined window (commonly 30 days of completion). An unregistered install is a visible install with no warranty behind it. Contractors sometimes skip registration to save administrative effort; owners discover it three years later when a claim is denied.

How is unit-price different from lump-sum on SB 721 work?

Lump-sum fixes the price for a defined scope; the contractor absorbs quantity-overrun risk. Unit-price sets a per-unit rate (for example, dollars per linear foot of replacement joist) and reconciles the final quantity at closeout. SB 721 repairs have inherently unknowable quantities. Dry rot extends where demolition shows it extends. The hybrid bid format uses lump-sum for the knowable portions (waterproofing system, flashing, painting) and unit-price for the variable portions (additional joists, additional membrane area, additional guardrail posts), with an allowance line for genuinely unknowable substrate repair.

Does SB 326 let a contractor perform the inspection?

No. Civil Code § 5551 restricts SB 326 inspections to licensed architects, structural engineers, or civil engineers. AB 2114 (2024) added civil engineers to that list. Contractors. Even A, B, or C-5 contractors. And certified building inspectors do not qualify for SB 326. SB 721 under HSC § 17973 is the statute that allows contractor inspections, and only for A, B, or C-5 contractors with 5+ years of multistory wood-frame experience.

What is an "approved applicator"?

An approved applicator is a contractor who has been trained and registered by the coating manufacturer for the specific system being installed. Most walking-deck ESRs and manufacturer warranties condition performance guarantees on approved-applicator install. The certification has an effective date and an expiration; verify both on bid evaluation. As a worked example, Deck Flex systems under ESR-3672 require (1) a manufacturer-approved licensed contractor and (2) a licensed specialty contractor applying elastomeric membrane roofing and waterproofing for a minimum of 5 years.

Are bid protests available on SB 721 repair work?

SB 721 repair contracts are private, not public. There is no statutory bid-protest process like the one that applies to public works under the Public Contract Code. Owners and HOA boards accept, reject, or re-bid at their discretion; any protest mechanism is contractual, built into the RFP itself if at all. If a fairness or transparency process matters to the owner, build it into the RFP document.

Balcony Repair Materials

Coatings, flashing, fasteners, and substrate-prep materials commonly specified on SB 721 and SB 326 balcony repair projects.

Deck Waterproofing Systems

View all 7
Clear Penetrating Protective Sealer
-11%

Clear Penetrating Protective Sealer

$200.00

$225.00

Deck Flex TetraCrete #2 White Specialty Cement

Deck Flex TetraCrete #2 White Specialty Cement

$60.00

Deck Flex TetraCrete #3 Gray Specialty Cement

Deck Flex TetraCrete #3 Gray Specialty Cement

$60.00

Elastomeric Premium Acrylic Deck Paint

Elastomeric Premium Acrylic Deck Paint

$300.00

SB 721 Repair Kit. Flashing, Fasteners, Prep

We don't have a curated product set for SB 721 Repair Kit yet. Search the catalog or browse related categories.

Search the catalog

Was this page helpful?

Your feedback helps us improve our technical resources.

Customer Support

Terms of ServicePrivacy PolicyShipping & DeliveryReturns & RefundsFAQs

Copyright © 2026 US Made, LLC. All Rights Reserved.

All content is for informational purposes only and does not constitute professional, legal, or compliance advice. Verify all requirements with the applicable standards and authorities.

Secure Payments

VisaMastercardAmerican ExpressDiscoverApple PayGoogle PayShop PayPayPal